Vision : To be the leading petroleum pipeline transportation company
with excellence performance through services, safety, environment and social responsibility.

Date

Milestones

1988-1989

The government appointed a working committee from government sector and oil companies to study for an efficient oil transportation system for the country.

5 June 1990

The Cabinet approved the construction of multi-products pipeline stretching from Sriracha, Chonburi Province, to Saraburi Province. PTT was assigned to set up a joint venture company for the operation of the facility.

9 January 1991

Thai Petroleum Pipeline Company Limited (Thappline) was established.

23 April 1992

The construction project began.

23 June 1994

The first batch of oil was pumped into the pipeline system from the Sriracha Pump station.

1 July 1994

Oil distribution services at Lumlukka Terminal, Pathumthani Province was started.

27 July 1994

Jet fuel transport to Don Mueang Airport began.

8 August 1994

Commenced fuel distribution at Saraburi Terminal.

15 May 1995

HRH Princess Maha Chakri Sirindhorn presided over the official grand opening ceremony.

15 September 2005

Map Ta Phut-Sriracha pipeline commenced operation.

16 September 2006

Jet fuel transport to Savarnabhumi Airport began.

December 2006

Total of 100,000 million liters of fuel were transported through the pipeline system.

9 January 2021

30th years anniversary of establishment

October 2022

Total 300,000 million liters of fuel were transported through the pipeline system.

August 2023

Operation for pipeline expansion from Saraburi oil terminal to Khonkhen oil terminal commenced.